In October
2010, Approved Document L of the Building Regulations (England & Wales) was
introduced. There were a number of
important changes to the 2006 version all of which aim to improve CO2
emissions by 25% over the 2006 regulations. The key changes include:
These
measures are part of the ‘fabric first’ approach which basically attempts to
get the building as thermally efficient as possible before adding on the
renewables and other energy-saving techniques. This is the most sensible
approach and it is anticipated that the next revision of Part L in 2013 will
continue this concept.
The table opposite shows the maximum permitted
u-values for walls and floors in Part L1A (New build dwellings) and Part L1B
(Existing dwellings).
In practice, lower u-values are aimed for to help
the required % reduction in CO2 from the SAP calculation be achieved
easily. Currently for new build dwellings, walls tend to be 0.28 and below, floors 0.22 and below.
On the right-hand side of this page are tables of u-value solutions for meeting these targets using our range of concrete blocks.
A new concept
introduced into Part L 2010 is the Party Wall bypass. The theory is that heat
can be lost from the dwelling up through the cavity party wall and that
therefore this heat loss must be accounted for in SAP.
Robust Detail Party Walls as approved for use with
Thomas Armstrong’s range of blocks have been updated to include fully-filled
options and therefore allow a party wall u-value of 0.00 W/m2K to be
applied.
Furthermore, solid wall options (traditional blocks laid flat or solid Airtec
blocks) allow a u-value of 0.00 W/m2K to be applied.
The limiting value for air permeability has been set at 10m3/hr.m2 tested at 50 pascals, and the requirements for on-site air permeability testing has been increased over previous regulations. For non-tested properties, the regulations say that an additional 2 m3/hr.m2 must be added to the figure achieved for tested figure for a same house type. Therefore in practice designers are aiming for a maximum of 8 m3/hr.m2 to ensure compliance with Part L.
Masonry block walls using any type of Thomas Armstrong concrete block have been shown to easily achieve these figures provided that good workmanship is employed. Figures of around 5 m3/hr.m2 are commonplace and are desirable.
A parge coat on the internal wall faces can contribute to exceptionally low air permeability figures of 2 or less which help to achieve Passivhaus and Code Level 4 requirements. However, the designer has to be aware that air quality might suffer and mechanical ventilation systems may have to be installed to avoid condensation and related health issues for the residents.
All of the above measures result in dwellings with higher thermal insulation and greater airtightness. This has increased the significance of heat loss at junctions and must be accounted for in SAP calculation.
Simply put, the detail of each building element junction in the property
(e.g. wall/window, wall/floor junctions etc) must be assessed for heat loss to
give a ψ (psi) value for that junction. The values are then added together to
give an overall linear thermal bridging figure for the property, its ‘y-value’.
There are 3 routes to determining the overall y-value of a building:
Option 1
Do
nothing, use a y-value of 0.15
If the designer does not account for each thermal bridge, then a default
y-value of 0.15 must be applied in SAP 2009 which will be significantly
disadvantageous in achieving desired DER and % reduction in CO2
requirements. The only way to gain a pass in SAP would be to use PV or
renewables at great expense.
|
Current Status:
|
Option 2
Use Accredited Details from table K1 in the guidance to SAP 2009
In the absence of any approved government scheme, it is permitted to use the
accredited values in table K1 found in the guidance for SAP 2009 for the
purposes of SAP calculations. An overall y-value of around 0.08 would be
expected. Once an ACD scheme is up and running, on-site inspections of the
as-built vs design will need to be carried out.
Option 3
Use specific modelled junctions
ψ values for specific junctions, using specific building materials can be
calculated by trained, approved persons. These can lead to y-values of 0.04 or
lower which can greatly reduce the need for PV etc in order to achieve SAP
target DER figures.
No site inspection is required but a 25%, or 0.02 confidence factor (whichever
is the greater) must be added to each ψ value. Nevertheless
using modelled junctions result in better values than any ACD scheme and can
result in significant cost savings for the builder.
At the time
of writing there is no government approved ACD scheme in place and the full Airtecψ values can be used without the 25% penalty.